APPLICATION METHOD
The walls, before applying the decorative plasters, should be qualitatively aligned and plastered.
Before applying the wall must be primed with compositions corresponding to the selected surface. It is desirable to complete the rough work before applying to avoid pollution. The manufacturability of the process must be maintained. Each applied layer must dry for obtaining durability. Under these rules coating becomes durable, high-quality and elegant.
Step 1: prime painting of the surface. Priming – to apply prime on a solid and well-dried basis by roller. Diluting with water up to 30%. The drying time – 8 hours. The surface must be free of roughness and grooves; as well it must be free of scratches.
Step 2: Application of the base layer of the decorative coating – apply on the surface with a brush with chaotic movements, followed by smoothing after 2-4 minutes. Smooth the grains of sand. Depending on the space dryness you can mix with water (5-10%): The drying time – not less than 4 – 6 hours.
Step 3: final layer and smoothing – Smoothly apply the third layer. It is not always possible to apply without gaps after the first layer.
* In the application of the first and the second layer it is necessary to wait from 4-8 hours. Drying time: on average: 30-60 minutes, complete drying: 7-14 days, depending on the type of surface.
* If the paint is in several buckets, before using it mix everything in one container.